The Public Service Commission of Wisconsin (PSCW) is the regulatory agency that reviews and approves major utility projects in the state of Wisconsin. ATC submitted an application for a Certificate of Public Convenience and Necessity, which generally includes all the documentation required for the PSCW and WDNR to review the project and make a decision. The PSCW notified affected individuals when the review process has started and will schedule public hearings so that the public may offer formal comments on the project. The application was approved by the PSCW in December 2025, written order here.

Project Schedule*

  • PSCW - CPCN Application Preparation
  • PSCW - Filing, Data Requests and Completeness Determination
  • PSCW - CPCN Order
  • Preconstruction Efforts - Right of Entry Coordination, Environmental, Reviews, Engineerings, Real Estate, Permits, Geotech, etc.
  • General Construction

*Subject to change, for more detailed information please see the Project Map.

** Target for in-service of the 345-kV line from Columbia to Arpin to Tremval substations. Rebuilt lines will be energized and in-service as completed.